Beginning this spring and lasting throughout the summer, ICC will complete several construction and/or remodeling projects on the East Peoria Campus. For safety concerns, please note that the following areas will be closed to all faculty, staff, and visitors during construction.
RTU Phase 7 — Roof Top Unit Replacement
- May 14 – June 7: Academic Building 2nd floor (237-238B) and 3rd floor (337A-338F)
- June 10 – July 5: Academic Building 2nd floor (239A-240B and 3rd floor (339A-340G)
- July 8 – July 19: Academic Building Atrium
Second Floor Plan
Third Floor Plan
Some Departments will be temporarily relocated:
- Controller moved to 106D
- Curriculum Services moved to L158
- Human Resources moved to 303 and 305 office suites
- Payroll moved to 305C
- Risk, Safety & Benefits moved to 319A
Phase C — Restroom Remodel
- May 14 – July 30: Academic Building restrooms between 125B-126, between 225F-226, between 325-326, and between 328-329
Phase 3 — Roadway/Parking Lot Resurfacing
- Early June 2019: storm drain along Centennial, Centennial entrance and exit, Power Dr, and Nature Ct